Expressway delays fibre rollout

May 10th, 2019 | By

A delay is likely in the roll out of the ultrafast broadband network in the Cherry Lane and Bollard Road areas.

The hold up comes because of work restrictions placed on contractors Ultra Fast Fibre from the Waikato Expressway construction in the same area.

“The latest we now expect to be able to connect anyone in this area is from 1st September,” said Mike Ryan of UFF.



SH1 goes middle of the road

May 17th, 2017 | By

State Highway 1 through Tamahere central is festooned with orange cones as tarsealing of the former median strip is carried out between the Airport Rd turn off and Bollard Rd.

This will allow traffic to be shifted from the road proper while trees are felled, phone and electricity cables are relocated, and the connection to the expressway constructed.

Some of the many cones will be replaced with permanent ‘SafeHits’.



Bridge pile driving restarts

Apr 24th, 2017 | By

Waikato Expressway pile driving will restart from Thursday for the bridge to span State Highway 1 at Cherry Lane.

Six piles will be driven 35 to 40 metres into the ground at the western abutment to complete piling at the East/West Link Bridge.

This will take about three weeks to complete bringing increased noise and vibration for nearby residents. (See piling video)



Bridge piles in early

Feb 9th, 2017 | By

Waikato Expressway contractors are making an early start on the piles for the bridge which will span State Highway 1 at Cherry Lane.

The thud of pile driving is now set to begin later this month as preparations for the East-West bridge get underway two months earlier than planned.

A big, blue, 100 tonne crawler crane will be assembled on the site alongside SH1 in northern Tamahere when piling is about to begin.



Expressway changes face of Tamahere

Jan 11th, 2017 | By

The once treed view alongside State Highway 1 close to Hamilton has rapidly given way to brown earthworks since early January as the latest section of the Waikato Expressway to effect Tamahere steps up pace.

Construction has begun of a new, two-lane Cambridge Rd off-ramp into Hamilton, east of the current SH1, opposite Cherry Lane.

The off-ramp is part of what will be something of a spaghetti junction which will eventually include an east/west bridge connecting Cherry Lane and Bollard Road with Cambridge Road and Birchwood Lane.



Spaghetti junction served again

Sep 11th, 2016 | By

The latest design for Tamahere’s upcoming spaghetti junction – the Waikato Expressway’s Hamilton section southern interchange – is again open for public viewing.
For those who missed the first information session a month ago, the design for the complex State Highway 1 interchange centred on Cherry Lane is set to transform the local road network in northern Tamahere.
NZTA and its contractors will reveal the latest design at an information day in the Tamahere Community Centre on Wednesday, September 14 from 2.30pm to 7pm.



Spaghetti junction on show

Aug 8th, 2016 | By

The latest design for Tamahere’s upcoming spaghetti junction – the Waikato Expressway’s Hamilton section southern interchange – is open for public viewing on Wednesday.

The complex State Highway 1 interchange centred on Cherry Lane is set to transform the local road network in northern Tamahere and property access for many who live there.

NZTA and its contractors will reveal the latest design at an information day in the Tamahere Community Centre on Wednesday, August 10 from 2.30pm to 7pm.



Killer corner work to begin

Oct 8th, 2014 | By

Work to bring changes to State Highway 1 and improve safety at the killer Cherry Lane intersection are set to begin on Sunday, October 19.

The long awaited changes, including reducing the SH1 speed limit to 80km/hour between Annebrook and Bollard roads, come after widespread calls for action prompted by concerns at the high number of serious crashes at the corner, including a fatal accident in April.

In a letter to Tamahere locals, Fulton Hogan said the work would be carried out at night between October 19 and 23, weather permitting.



Speed cut for killer corner

Aug 22nd, 2014 | By

The NZ Transport Agency will cut the speed limit on State Highway 1 to 80km/h past the Cherry Lane killer corner.

The SH1 speed reduction, along with the removal of the southbound passing lane, were among safety improvements investigated after widespread calls for action on the corner prompted by concerns at the high number of serious crashes, including a fatal accident in April.

NZTA Principal Safety Engineer Michelle Te Wharau said today that after community consultation it had been decided to go ahead with the most far reaching safety measures.



Killer corner no safer

Jul 25th, 2014 | By

None of the measures mooted to increase driver safety at the Cherry Lane – State Highway 1 killer corner have been done a month after many were expected to be in place.

In early May, the NZ Transport Agency detailed short and long term actions ranging from road signs to reduced speed limits but a month after NZTA’s own deadline Cherry Lane residents are still waiting.

The measures agreed with a residents’ group followed widespread calls for action on the corner prompted by concerns at the high number of serious crashes, including a fatal accident in April.